This article is for using the Timesheet feature on the On My Plate page.
If you want to add time to a task inside a project, go to this article.
The following are steps for adding time for a non-project activity, such as company training.
- Go to the On My Plate page.
- Click the Timesheet tab.
- Click the Add Time Item button. (See first image below.)
- In the popup, click the Add Non-Project Activity option. (See second image below.)
- If the system found a non-project line item from last week, it will give you the option to add it for this week. This is optional.
- Enter the project name.
- When you click on the "Enter activity label" line, it will first show you in a dropdown other activity labels used before so you can choose the same labeling. If not, you can enter your own new non-project activity label
- You can then keep the default "Non-Billable" tag, remove it, or add other tags. If you see other tags in the dropdown, that's because you or someone else created tags for other tasks in your organization. Keeping everyone on the same page for using the same tag when possible will help with future reports.
- Once your tag is ready, click the green "Add" button and it will be added as a line item. You can then click in the cells to enter hours.
Comments
0 comments
Please sign in to leave a comment.